Currently in progress, final grading of Ballfields, pond excavation and the installation of main irrigation line.  Field Lighting Pole installation is almost complete.  Irrigation and grading at the North parking lot is complete and sod has been layed.  The remainder of the South parking lot has been poured.  Electrical underground at slab has been installed and was green tagged.  Make up of slab area has begun and concrete pour has taken place.  Retaining wall installation has begun and excavation for submergible pump at Lake is complete.  The intake pipe into the lake has been installed.  Pipe installation towards the irrigation pond has taken place.  The outfield fence with mow strip at Field A and B will begin this week.  Master Turf will be delivering Clay Mix this week.






  